As a reminder, the Group announced on 19 of May 2022 that the start of electricity production was scheduled for June 2027. At that time, the risk of further delay in the delivery of the two units was estimated at 15 months. The cost of completion of the project was estimated between £25 and £26 billion in 2015. A review of the Hinkley Point C project has been finalised and has led to the following re-evaluation of the schedule and … read more »