A call for a statutory review of the Overarching National Policy Statement for Energy (EN-1)

Members of TASC have written a Submission to Amber Rudd, The Secretary of State for Energy, calling for a review of the governments policy on nuclear power new build.

Decisions regarding the need for extensive new supply-side infrastructure have driven energy policy for decades and left the demand-side of energy policy inadequately addressed.

This has resulted in a policy requiring the installation of new (supply side) generating capacity without first properly assessing:

  1. Whether such infrastructure is needed in the first place; and

  2. The potential for the demand side alternatives (such as energy efficiency and energy saving) that the government itself says are the cheapest and most cost effective ways of delivering energy policy objectives

New evidence produced by DECC shows that new nuclear power stations will:

1. risk ‘the lights going out’;

2. waste £billions;

3. hamper the achievement of the Government’s stated energy policy objectives;

4. be less effective in meeting energy policy objectives than a more ‘demand-side-led’ strategy; and

5. not satisfy the ‘urgent need’ for new electricity supplies that the Government says are necessary.

Unlike a non-nuclear approach to energy policy

A copy of the submission can be downloaded here


Daily Telegraph 09 Jul 2015

French state-owned nuclear giant Areva has been aware for almost a decade of critical anomalies in its new generation EPR plant in Flamanville, the same model sold to Britain


From The Guardian, 2 July 2015

Nine German and Austrian utilities selling renewable energy join with green group to launch legal action against state aid for new nuclear power in UK

A law suit against ‘boundless nuclear subsidies’ for the project is to be filed within days.

Greenpeace and nine German and Austrian utilities selling renewable energy said on Thursday they are launching legal action against state aid for a new British nuclear power plant, which was approved by the European commission.

Greenpeace and the others in the group said at a news briefing that the lawsuit would be filed with the European Court of Justice in Luxembourg in the coming days, over the Hinkley Point C project in south-west England.

It would be based on the argument that billions of euros of subsidies for nuclear energy would distort prices in mainland European power markets, which are linked to those in Britain via a small French interconnector.

“We are complaining against these boundless nuclear subsidies, because from an ecological and macro-economic viewpoint, they appear senseless and bring substantial financial disadvantages for other energy suppliers, renewable energies and for consumers,” said Soenke Tangermann, managing director of the Greenpeace Energy co-operative.

The project, due to be built by French utility EDF, is deemed crucial for Britain’s plan to replace a fifth of its nuclear power and coal plants in the coming decade.

Germany’s decision to phase out nuclear and to focus on wind and solar power sets it at odds with decisions in Britain and France to invest in emissions-free nuclear, which they have chosen to play a major role in combating climate change.

The European commission last year approved state aid for the £16bn Hinkley Point plan.

EU member states can choose their individual power generation mix, but have to obey rules respecting the European drive for harmonised internal markets.

The campaigners said price guarantees for Hinkley Point C’s output, calculated over 35 years, would amount to €108bn (£77bn) while state guarantees for the construction of the reactor exceeded another €20bn.

They said the Hinkley Point C could become a precedent for nuclear projects in Poland, the Czech Republic and Hungary, which would run counter to Germany’s intended transition to a renewable-based energy future.

Artificially low prices of electricity derived from subsidised nuclear plants would push up prices German consumers were paying for green energy, they said.

Greenpeace Energy supplies 111,000 customers with renewable power.

The other nine companies in the alliance are Energieversorgung Filstal, municipal utilities (called Stadtwerke) of Aalen, Bietigheim-Bissingen, Bochum, Mainz, Muehlacker, Schwaebisch Hall and Tuebingen, and Austria’s oekostrom.

Daily Telegraph, 10 June 2015

Flamanville third-generation EPR nuclear reactor - the same model Britain plans to use for two new plants at Hinkley Point - has multiple faults in crucial safety valves, inspectors warn

Nuclear safety inspectors have found crucial faults in the cooling system of France’s flagship new-generation nuclear power plant on the Channel coast, exposing it to the risk of meltdown. The third-generation European Pressurised Reactor currently under construction in Flamanville is the same model that Britain plans to use for two new plants at Hinkley Point in Somerset. State-controlled nuclear giant Areva is responsible for the design and construction.

France’s nuclear safety watchdog found “multiple” malfunctioning valves in the Flamanville EPR that could cause its meltdown, in a similar scenario to the 1979 Three Mile Island nuclear accident in the US. The inspectors listed the faults in a damning presentation obtained by Mediapart, the investigative French website.

This is the latest setback for what is supposed to be France's atomic energy showcase abroad, following the revelation last month that its steel reactor vessel has “very serious anomalies” that raise the risk of it cracking. The vessel houses the plant's nuclear fuel and confines its radioactivity.

The findings were listed in a presentation by the French Institute for Radiological Protection and Nuclear Safety (IRSN) to France’s top nuclear safety regulator (ASN). The watchdog reportedly cited “multiple failure modes” that could have “grave consequences” on the safety relief valves, which play a key role in regulating pressure in the reactor.

Owned by state-controlled French utilities giant EDF, Flamanville lies close to the British Channel Islands and about 150 miles from the southern English coast.

Designed to be the safest reactors in the world and among the most energy-efficient, the €9 billion (£6.5 billion) EPR has suffered huge delays in models under construction in France, Finland and China. It is now due to enter service in 2017, five years later than originally planned.

In April, it was revealed that excessive amounts of carbon in the steel in the top and bottom of the reactor’s vessel, which forms a shell around it, could cause cracks which could prove disastrous, as the vessel cannot be replaced during the lifespan of the reactor.

The faulty safety relief valves are situated on the pressuriser, which regulates the high pressure within the primary circuit where water cools the nuclear fuel by releasing steam when necessary.

The failure of a pilot-operated relief valve in the primary circuit was a key factor in the partial meltdown of a reactor at the Three Mile Island plant in the US in March 1979, and which led to the halting of America’s civil nuclear power programme.

In that accident, nuclear reactor coolant escaped through a valve that was stuck open, sending the reactor into partial meltdown.

At Flamanville, IRSN noted “opening” and “closing” failures concerning the pilots that operate the safety valves and “risks of fluid leaks” of the reactor coolant. It warned that the multiple faults could have “grave consequences”.

On Tuesday, IRSN confirmed tests conducted by EDF showed “difficulties in opening and shutting valves”. But it played down the gravity of the findings, saying : "For now, one cannot conclude it is serious as we haven’t fully judged the quality “of the valves” – a view it will announce this summer. “We are examining dossier handed in by EDF with a view to starting up the EPR. There are remarks on all subjects. It’s classic,” said Thierry Charles, deputy director general of IRSN.

Last week, the French government announced Areva NP, the nuclear reactor arm of state-controlled Areva, is to be sold to EDF, its former client which also operates all of France’s 58 nuclear reactors. The move followed Areva’s announcement in March that it had racked up record losses in 2014 of €4.8 billion.

EDF is in the final phase of negotiations with the British government on building the two Hinkley plants in Britain, which in February it said would be "possible in the next few months".

Reported in Reuters on May 27



Austria will take legal action to block any subsidized nuclear power plants in an effort to discourage use of the technology in Europe and scare off investors, the country's environment minister, Andrae Rupprechter, said in a newspaper interview.

Rupprechter's comments to business daily Wirtschaftsblatt reflect non-nuclear Austria's tough stance, as evidenced by its intent to take the European Commission to court over approval of Britain's plans for the Hinkley Point nuclear plant.

Neighboring Czech Republic also plans to extend its nuclear capacity.

"Should other countries present similar subsidy plans, we will fight these in court," the minister said in the interview published on Wednesday, saying such state backing hindered the rollout of renewable energy technology.

"Giving preference to nuclear power is unacceptable. Nuclear energy is neither safe nor economical. A lawsuit may also make potential investors hesitant."